Recommended Preparation and Schedule for Project 3

MCS 177: Computer Science I, Spring 2003
Assignment:  Project 3: Fractal curves
 
Schedule for Project 3:
March 24 (prior to first lab): Read section 4.3

March 25: Do exercises 4.5, 4.6, and 4.7

March 27: Do exercises 4.8 and 4.9 and start 4.10

April 8: Finish exercise 4.10 and do project write-up

April 9: Project 3 due in class
 
Helpful information
Lab instructor: Karl Knight
R4RS Scheme documentation